Days of cover

How long current stock lasts vs. how fast it can be replenished. Every number is verifiable arithmetic — no black box.

All items

20 tracked · sorted by risk exposure

Risk exposureItemOn handMonthly usageDays of coverLead timePrimary supplierSupplier dependency
Critical

8 kW hybrid inverter

Mission-critical

INV-HYB-8K

2,4001,80040 d90 dJiangsu SunCore InvertersSingle-sourced
  • Stock runs out in 40 days but earliest replenishment is in 90 days (50-day gap).
  • Item is single-sourced — no alternative supplier on file.
Critical

50 kVA distribution transformer

Mission-critical

TRF-50K

25015050 d85 dChennai Transformers LtdSingle-sourced
  • Stock runs out in 50 days but earliest replenishment is in 85 days (35-day gap).
  • Item is single-sourced — no alternative supplier on file.
Critical

50 kW string inverter

Mission-critical

INV-STR-50K

1,50060075 d90 dJiangsu SunCore Inverters2 suppliers
  • Stock runs out in 75 days but earliest replenishment is in 90 days (15-day gap).
At risk

12-string combiner box

CMB-12STR

3,0001,80050 d45 dDongguan Combiner MfgSingle-sourced
  • Cover (50 days) dips below safety stock (14 days) before replenishment arrives.
  • Item is single-sourced — no alternative supplier on file.
At risk

Monitoring gateway

Mission-critical

MON-GW-01

6,0003,00060 d50 dSeoul Monitoring Systems2 suppliers
  • Cover (60 days) dips below safety stock (21 days) before replenishment arrives.
At risk

100 kW utility inverter

Mission-critical

INV-UTIL-100K

27012067 d40 dPhoenix Inverter SystemsSingle-sourced
  • Cover (68 days) dips below safety stock (30 days) before replenishment arrives.
  • Item is single-sourced — no alternative supplier on file.
At risk

800W microinverter

Mission-critical

INV-MICRO-800

24,0009,00080 d70 dTaipei Microinverter Inc.Single-sourced
  • Cover (80 days) dips below safety stock (21 days) before replenishment arrives.
  • Item is single-sourced — no alternative supplier on file.
At risk

10 kWh LFP battery

Mission-critical

BAT-LFP-10K

6,8002,40085 d75 dGuangzhou PowerCellSingle-sourced
  • Cover (85 days) dips below safety stock (21 days) before replenishment arrives.
  • Item is single-sourced — no alternative supplier on file.
At risk

15 kWh LFP battery

Mission-critical

BAT-LFP-15K

3,6001,20090 d75 dGuangzhou PowerCellSingle-sourced
  • Cover (90 days) dips below safety stock (21 days) before replenishment arrives.
  • Item is single-sourced — no alternative supplier on file.
Watch

DC isolator 1000V

ISO-DC-1000

18,6009,00062 d45 dDongguan Combiner MfgSingle-sourced
  • Cover (62 days) is within 1.5x of replenishment lead time (45 days) — any delay creates risk.
  • Item is single-sourced — no alternative supplier on file.
Secure

Mid clamp

MNT-CLAMP-MID

120,000120,00030 d14 dKrakow Mounting HardwareSingle-sourced
Secure

MC4 connector pair

CON-MC4

360,000300,00036 d14 dShenzhen Connect Co.3 suppliers
Secure

DC solar cable 6mm²

CBL-DC-6MM

280,000200,00042 d10 dHamburg Cable & Connectors2 suppliers
Secure

Roof hook

MNT-HOOK-RF

180,00060,00090 d55 dBac Ninh Mounting Systems2 suppliers
Secure

Mounting rail 4m

MNT-RAIL-4M

72,00024,00090 d55 dBac Ninh Mounting Systems2 suppliers
Secure

3-phase smart meter

MTR-3PH

15,2004,500101 d50 dSeoul Monitoring Systems2 suppliers
Secure

Power optimizer

Mission-critical

OPT-PWR-01

136,00036,000113 d60 dWuxi Optimizer Works2 suppliers
Secure

450W mono PV module

Mission-critical

MOD-450-MONO

120,00030,000120 d75 dHefei Solar Modules3 suppliers
Secure

550W bifacial module

Mission-critical

MOD-550-BIF

250,00045,000166 d75 dHefei Solar Modules2 suppliers
Secure

Ground-mount structure kit

MNT-GROUND-KIT

20,000800750 d35 dSao Paulo Solar StructuresSingle-sourced